DETAIL DESIGN FOR THE NEW RAILWAY BRIDGE OVER TORDERA RIVER. SPAIN

CLIENT ADIF
SERVICE Emergency and repair project
DATE 2020
LOCATION Girona, Spain

On January 22, 2020, the torrential rains associated with the storm Gloria disrupted service on the Line 276: Sagrera Junction – Maçanet Massanes caused by the flooding of Tordera River that collapsed the existing bridge at P.K. 059/183. This event prompted an emergency project with the aim of restoring service as soon as possible. After analyzing the root cause of the problem and considering the likelihood of a similar event happening again, the decision was made to replace the current bridge with a new one, reducing the number of spans from 14 to 5, what improves the hydraulic section, and reduces the risk of a dam effect.

The new bridge is a prestressed and reinforced concrete structure, with a length of 221.30 meters distributed across 5 spans with the following spans: 33.15 m + 51 m + 51 m + 51 m + 33.15 m. Since this was an emergency project, the design phase overlapped with the construction phase, taking just 8 months to complete the works and restore the railway service.